Piedmont Community Pool: A look back at how we got here

Matt Hofherr

With the Piedmont Community Pool stalled in the commissioning phase — and resident impatience mounting — we’ve compiled a timeline of the project based on our reporting since 2020, when the old pool was closed in response to the pandemic and city deliberations began over the future of the site.

The city’s commitment to sustainability via its Climate Action Plan (updated in 2018) played an important role in the decision to build an all-electric pool. Many community members wrote letters and attended meetings and workshops to advocate for a “green” pool.

The ambitious project moved along steadily until late 2023 and into 2024 when unforeseen construction site issues appeared and costs rose. Although the construction phase of the project was largely wrapped up in September 2025 when the new pools were filled with water, an opening date remains elusive as project managers work to get the facility’s mechanical and pool systems all working together. The last official update from the city was in November 2025; the city said in an email on Friday that it would be providing another update this week.

Background

The community pool first opened in 1964. Until 2011, it was operated by the private Piedmont Swim Club. In 2011, the city assumed responsibility for the pool’s operation.

Starting in 2002, the Piedmont community launched several efforts to build a new aquatics center, including an “Aquatics Master Plan Conceptual Design” in November 2016. In 2018, a consultant told Piedmont officials it would cost more than $1.5 million for needed renovations to extend the aging pool’s life by at least five years.

When COVID forced the pool closure, the city had to make a decision whether or not to reopen the aging pool. At a special meeting in June 2020, the City Council heard a report about whether to keep the 56-year-old pool open. They were told that assuming “no catastrophic failure of the pool vessel structures themselves,” it was expected the city could spend more than $4 million over the next 10 years to keep the pool “marginally functional,” with significant annual operating shortfalls a virtual certainty.

The old Piedmont Pool in August 2020

After that meeting, Council asked for more information from city staff before making a decision around reopening the pool.

In July 2020, the Council prioritized the pool among other facilities projects, saying it was essential for Piedmont’s community fabric and that the prospects of wringing more mileage out of the aging facility were slim to none. It voted to put a bond measure for the pool on the Nov. 3 ballot that year.

The community and Council continued to debate whether to reopen the old pool even as plans were in motion to build a new one. The Council decided in September 2020 to keep it closed for a variety of reasons, among them the difficulty in hiring staff and managing swimmers due to COVID, a malfunctioning heater, and the fact that the pool was leaking about 3,000 gallons of water a day.

Timeline of planning for the new pool complex
  • November 2020: Measure UU passes with 68.47 percent Piedmont voter approval. It called for authorizing the city to issue up to $19.5 million in general obligation bonds to finance construction of a new city swimming pool. 
The old Piedmont pools were drained of water in September 2021 (Julie Reichle)
  • October 2021: The city selects ELS Architecture and Urban Design over seven other firms which had sought to be the lead architect for the $19.5 million pool project, which city leaders said they hoped would be finished in mid-2024.
  • January 2022: The city creates an FAQ page to address common questions that arose during community workshops.
  • March 2022: Budget constraints pare back the original pool plan. In the face of fast-rising construction costs and a tight construction budget, the Council agrees to eliminate most of the second story of the pool complex building and fast-track the project out to bid.
  • March 2022: Whether the pool would be heated with natural gas or by electric power is still under consideration. Residents who spoke at a Council meeting said it was worth spending the extra upfront costs for the needed infrastructure in the name of environmental protection in the big picture, and to adhere to the city’s Climate Action Plan 2.0 on a more local level.
  • April 2022: City Council votes to move forward with an all-electric pool. The decision put Piedmont at the forefront of heating large public swimming pools with electricity. In California, only the city of Mountain View had adopted a similar plan. Councilmembers acknowledged some risk in going down that path, but community support for a sustainable pool was strong.
  • May 2022: Council approves modification to design. The project’s design changes and accelerated timeline were undertaken to save at least $6 million from what has ballooned to a projected $25 million project construction cost. The biggest change was eliminating most of the second story of the main building, including three conference rooms, an elevator, and a stairway. The entire Community Pool Project budget is now $24.5 million, and the council is working to cap construction costs at about $19 million.
  • October 2022: City Council votes to rebid pool project. The estimated cost to build the pool and associated buildings is about $21.6 million. Original bids exceeded the $21.6 million figure by more than 15 percent so the city’s pool project team recommended rejecting both bids and modifying the bid documents to expand eligibility to a wider range of prospective contractors.
  • Dec. 17, 2022: City hosts groundbreaking ceremony. Around one hundred pool supporters and donors showed up in the Magnolia Avenue parking lot for a last look at the old pool and to mark the official beginning of the long-awaited construction project.
The Carriage House demolition is complete as of March 14, 2023
City employees and councilmembers observe the high velocity application of the shotcrete in September 2023
Construction crews oversee the pouring of concrete on Friday, Dec. 22, 2023 (City of Piedmont)
  • January 2024: City marks another milestone with beam signing ceremony. Members of the City Council, Pool Advisory Committee, Bond Oversight Committee, student athletes, and donors gathered to sign the top beam before it’s placed on the structure, a longstanding construction industry tradition.
A beam signed by students (City of Piedmont)
  • March 2024: Pool opening date is now TBD as construction continues. The original timeline has been amended over time due to rain and other complications, including the removal of buried fuel tanks and related contaminated soils that required permitting and coordination with Alameda County Environmental Health, according to the city’s update to Council.
  • July 2024: City Council approves an additional $2.1 million for the project. Construction delays related to underground fuel tanks, delays with PG&E, and weather (plus the discovery of an underground spring) have increased costs all around, city staff and the project managers said, necessitating additional contingency funds.
A chart from the Dec. 2, 2024 report to City Council from the city administrator
  • May 2025: City Council approves annual pass and drop-in fees for pool. The community pool pass model includes a 15% increase over 2019 base rates and a 40% non-resident pool pass premium, along with a proposed drop-in fee structure. Under this model, a yearly resident family pass will cost $1,337; a non-resident family pass will cost $1,872. (See chart below for full fee structure.)
  • June 2025: PHS water sports take a hit with pool delay. The lack of a local pool — athletes have had to travel to either Laney College or Berkeley High School for practices since 2021 when the pool closed — played a role in the decline, according to feedback from families and coaches. 
Pools filled with water in early September 2025. (City of Piedmont)
The new pool looks ready for use in January 2026 but an opening date remains elusive. (Julie Reichle)

Leave a Reply

The Exedra comments section is an essential part of the site. The goal of our comments policy is to help ensure it is a vibrant yet civil space. To participate, we ask that Exedra commenters please provide a first and last name. Please note that comments expressing congratulations or condolences may be published without full names. (View our full Comments Policy.)

Your email address will not be published. Required fields are marked *